印尼金川紅土鎳礦冶廠1#線鎳鐵電爐砌築完成
2026-05-02 01:36:28
印尼金川紅土鎳礦冶煉廠鎳鐵電爐爐體砌築任務由金川集團鎳都實業公司築爐隊進行施工作業,每台電爐爐體需用砌築各類塊耐火磚約13.4萬,需用搗打料及其它鋪底粉料約1470噸。第一台砌築的4#鎳鐵電爐施工周期43天(tian),項(xiang)目(mu)部(bu)為(wei)保(bao)證(zheng)施(shi)工(gong)質(zhi)量(liang)和(he)進(jin)度(du),對(dui)鎳(nie)鐵(tie)電(dian)爐(lu)施(shi)工(gong)過(guo)程(cheng)進(jin)行(xing)總(zong)結(jie)。做(zuo)到(dao)每(mei)砌(qi)築(zhu)一(yi)台(tai)鎳(nie)鐵(tie)電(dian)爐(lu),總(zong)結(jie)優(you)化(hua)一(yi)次(ci)施(shi)工(gong)方(fang)案(an),通(tong)過(guo)調(tiao)整(zheng)各(ge)工(gong)種(zhong)配(pei)比(bi),優(you)化(hua)施(shi)工(gong)工(gong)序(xu),嚴(yan)抓(zhua)施(shi)工(gong)質(zhi)量(liang),最(zui)終(zhong)將(jiang)1#鎳鐵電爐砌築周期縮短至23天。
10月14日10時,業主、監理、總zong承cheng包bao及ji專zhuan業ye質zhi檢jian人ren員yuan組zu成cheng驗yan收shou小xiao組zu對dui鎳nie鐵tie電dian爐lu爐lu內nei砌qi築zhu及ji幹gan燥zao燃ran燒shao室shi砌qi築zhu進jin行xing專zhuan項xiang質zhi量liang驗yan收shou,均jun一yi次ci通tong過guo驗yan收shou。在zai項xiang目mu部bu全quan體ti成cheng員yuan的de共gong同tong努nu力li下xia,印yin尼ni金jin川chuan紅hong土tu鎳nie礦kuang冶ye煉lian廠chang項xiang目mu各ge項xiang施shi工gong任ren務wu按an照zhao施shi工gong計ji劃hua節jie點dian有you序xu推tui進jin,為wei冶ye廠chang1#生產線產出合格鎳鐵奠定了基礎。
印尼金川WP&RKA紅土鎳礦項目至目前項目已生產鎳鐵產品14000噸,預計10月中旬將實現第一批鎳鐵銷售。
相關文檔
版權說明
【2】 凡本網注明"來源:XXX(非中國鋼鐵新聞網)"的作品,均轉載自其它媒體,轉載目的在於傳遞更多信息,並不代表本網 讚同其觀點,不構成投資建議。
【3】 如果您對新聞發表評論,請遵守國家相關法律、法規,尊重網上道德,並承擔一切因您的行為而直接或間接引起的法律 責任。
【4】 如因作品內容、版權和其它問題需要同本網聯係的。電話:010—010-64411649
地址:北京市朝陽區安貞裏三區26樓 郵編:100029 電話:(010)64442120/(010)64442123 傳真:(010)64411645 電子郵箱:
中國冶金報/中國鋼鐵新聞網法律顧問:大成律師事務所 楊貴生律師 電話: Email:
中國鋼鐵新聞網版權所有,未經書麵授權禁止使用 京ICP備07016269 京公網安備11010502033228